Detailed MEP and Controls Logic for Data Center Schedules

In data center construction, one of the most common scheduling challenges is oversimplifying the integration of mechanical, electrical, and low-voltage controls. These scopes are often shown as single finish activities or broad Gantt chart bars. When that happens, the schedule hides real constraints, distorts float, and removes early warning indicators. MEP and controls directly drive energization and commissioning, so they ...